Imagine your production team finds out on a Monday morning that critical components are missing to fill the week's orders. The supplier needs five days' notice and you needed that material yesterday. The line stops, costs spike and the customer gets their order late. This scenario, sadly common in manufacturing companies, has a direct solution inside SAP Business One MRP: the Material Requirements Planning Wizard.
MRP is not just one more feature of the system; it is the mechanism that connects your customers' real demand with your supply chain's ability to respond. Yet many companies already running SAP Business One never configure or run this wizard, leaving one of the ERP's most powerful tools on the table.

Why the MRP Wizard Changes the Rules of the Game
The MRP Wizard in SAP Business One automatically analyses three fundamental variables: existing demand (sales orders, production orders, forecasts), available supply (current stock, open purchase orders, planned production) and each item's planning parameters. The result is concrete recommendations: what to buy, what to produce and what to transfer between warehouses.
So instead of relying on manual spreadsheets or on the buyer's experience, you get a calculation engine that takes every piece of information in the system into account in real time. And each recommendation can be turned directly into a SAP document: purchase order, production order or inventory transfer request.
Prerequisites Before Running MRP
Before launching the wizard, you need your master data configured properly. Without that foundation, MRP will produce incorrect or incomplete recommendations. Here are the essentials:
1. Item planning data: In the master record of every item you want to include in planning, go to the Planning Datatab. Set the Planning Method field to «MRP» instead of «None». Also define the Procurement Method: «Make» for products you produce in-house or «Buy» for raw materials and external components.
2. Lead times: Configure the Lead Time for each item. For purchased items, this is how long the supplier takes to deliver the material. For produced items, it is the manufacturing time. If you do not define these values, MRP will assume immediate delivery and its recommendations will be unrealistic.
3. Bills of materials: For manufactured items, make sure you have Production-type bills of materials (BOM) created. MRP breaks finished-goods demand down into component requirements using these lists. For example, if you have an order for 100 units of a finished product, MRP will calculate how many units of each component you need.
4. Minimum and maximum levels (optional): In the Inventory Data tab you can define minimum levels that MRP will use as additional demand to keep safety stock. Use this feature sparingly, though, so you don't generate excess inventory.
Step-by-Step Tutorial: Running the MRP Wizard

Step 1: Open the wizard. Go MRP → MRP Wizard from the main menu. The first screen opens, where you can select an existing scenario or create a new one. I recommend creating a specific scenario for your planning cycle (weekly, biweekly or monthly).
Step 2: Define the planning horizon. Set the start date (usually today) and the end date of the horizon. For example, if you plan four weeks ahead, set the end date 28 days out. Then select the period granularity: days, weeks or months. For manufacturing, weeks is usually the most practical option.
Step 3: Select items. Choose whether you include every item flagged as relevant for MRP or only a specific group. You can filter by item group, warehouse or preferred vendor. You can also exclude discontinued or slow-moving items.
Step 4: Configure supply and demand sources. Define which documents the system treats as demand (sales orders, dependent production orders, inventory reservations) and as supply (open purchase orders, planned receipts, production orders in process). You can also include sales forecasts if you have them set up.
Step 5: Configure warehouses. Select the relevant warehouses and, for each one, indicate whether MRP should consider its inventory, its supply and its demand. That way you can run planning by plant or by distribution centre independently.
Step 6: Run and review results. Once configuration is complete, the wizard runs the calculation and presents the results in a table with columns for opening stock, demand, supply and closing stock per period. Items with a shortfall appear with recommended actions. You can review each recommendation before turning it into a document.
Step 7: Generate documents. Select the recommendations you want to execute and the system automatically creates purchase orders for external materials and production orders for items made in-house. Always review quantities and dates before confirming, though.
SQL Queries to Monitor Your MRP Planning
Once you run MRP and generate documents, you need visibility over the status of your orders. Below, two essential queries every SAP Business One user should have set up in their Query Manager.
Query 1: Production Order Summary by Status
This query lets you see at a glance how many production orders you have planned, released and in process, along with the quantities still to complete. It is ideal for daily production meetings.
SQL Server
-- Production order summary by status with completion analysis
SELECT
CASE T0."Status"
WHEN 'P' THEN 'Planned'
WHEN 'R' THEN 'Released'
WHEN 'L' THEN 'Closed'
WHEN 'C' THEN 'Cancelled'
END AS 'Status',
COUNT(T0."DocEntry") AS 'Total Orders',
SUM(T0."PlannedQty") AS 'Planned Quantity',
SUM(T0."CmpltQty") AS 'Completed Quantity',
SUM(T0."PlannedQty" - T0."CmpltQty") AS 'Pending',
CAST(
CASE WHEN SUM(T0."PlannedQty") > 0
THEN (SUM(T0."CmpltQty") * 100.0 / SUM(T0."PlannedQty"))
ELSE 0
END AS DECIMAL(10,2)
) AS '% Completion'
FROM OWOR T0 WITH (NOLOCK)
WHERE T0."Status" IN ('P', 'R')
AND T0."DueDate" >= DATEADD(DAY, -30, GETDATE())
GROUP BY T0."Status"
ORDER BY 1
SAP HANA
-- Production order summary by status with completion analysis
SELECT
CASE T0."Status"
WHEN 'P' THEN 'Planned'
WHEN 'R' THEN 'Released'
WHEN 'L' THEN 'Closed'
WHEN 'C' THEN 'Cancelled'
END AS "Status",
COUNT(T0."DocEntry") AS "Total Orders",
SUM(T0."PlannedQty") AS "Planned Quantity",
SUM(T0."CmpltQty") AS "Completed Quantity",
SUM(T0."PlannedQty" - T0."CmpltQty") AS "Pending",
CAST(
CASE WHEN SUM(T0."PlannedQty") > 0
THEN (SUM(T0."CmpltQty") * 100.0 / SUM(T0."PlannedQty"))
ELSE 0
END AS DECIMAL(10,2)
) AS "% Completion"
FROM "OWOR" T0
WHERE T0."Status" IN ('P', 'R')
AND T0."DueDate" >= ADD_DAYS(CURRENT_DATE, -30)
GROUP BY T0."Status"
ORDER BY 1
Query 2: Items with Stock Shortfall vs. Open Demand
This query compares each item's available stock against open demand in sales orders and production orders. It identifies the items that need urgent replenishment before you run MRP, giving you a fast diagnosis of your inventory status.
SQL Server
-- Items with a shortfall: current stock vs open demand
SELECT
T0."ItemCode" AS 'Item Code',
T0."ItemName" AS 'Description',
T0."OnHand" AS 'Current Stock',
T0."IsCommited" AS 'Committed',
T0."OnOrder" AS 'On Purchase Order',
T0."OnHand" - T0."IsCommited" AS 'Truly Available',
T0."OnHand" + T0."OnOrder" - T0."IsCommited" AS 'Projection',
CASE
WHEN (T0."OnHand" - T0."IsCommited") < 0
THEN 'CRITICAL SHORTFALL'
WHEN (T0."OnHand" - T0."IsCommited") < T0."MinLevel"
THEN 'BELOW MINIMUM'
ELSE 'OK'
END AS 'Alert'
FROM OITM T0 WITH (NOLOCK)
WHERE T0."frozenFor" = 'N'
AND T0."InvntItem" = 'Y'
AND T0."validFor" = 'Y'
AND (T0."OnHand" - T0."IsCommited") < T0."MinLevel"
ORDER BY (T0."OnHand" - T0."IsCommited") ASC
SAP HANA
-- Items with a shortfall: current stock vs open demand
SELECT
T0."ItemCode" AS "Item Code",
T0."ItemName" AS "Description",
T0."OnHand" AS "Current Stock",
T0."IsCommited" AS "Committed",
T0."OnOrder" AS "On Purchase Order",
T0."OnHand" - T0."IsCommited" AS "Truly Available",
T0."OnHand" + T0."OnOrder" - T0."IsCommited" AS "Projection",
CASE
WHEN (T0."OnHand" - T0."IsCommited") < 0
THEN 'CRITICAL SHORTFALL'
WHEN (T0."OnHand" - T0."IsCommited") < T0."MinLevel"
THEN 'BELOW MINIMUM'
ELSE 'OK'
END AS "Alert"
FROM "OITM" T0
WHERE T0."frozenFor" = 'N'
AND T0."InvntItem" = 'Y'
AND T0."validFor" = 'Y'
AND (T0."OnHand" - T0."IsCommited") < T0."MinLevel"
ORDER BY (T0."OnHand" - T0."IsCommited") ASC
Query 3: Outstanding Component Detail by Production Order
When you have released production orders, this query shows you exactly which components are still to be issued to the shop floor. You can spot bottlenecks in your production line before they turn into stoppages. It also includes the progress percentage of each component.
SQL Server
-- Componentes pendientes por orden de producción liberada
SELECT
T0."DocNum" AS 'Orden Producción',
T0."ItemCode" AS 'Producto Terminado',
T1."ItemCode" AS 'Componente',
T2."ItemName" AS 'Descripción Componente',
T1."BaseQty" AS 'Cantidad Requerida',
T1."IssuedQty" AS 'Cantidad Entregada',
T1."BaseQty" - T1."IssuedQty" AS 'Pendiente',
T2."OnHand" AS 'Stock Disponible',
CAST(
CASE WHEN T1."BaseQty" > 0
THEN (T1."IssuedQty" * 100.0 / T1."BaseQty")
ELSE 0
END AS DECIMAL(10,2)
) AS '% Avance',
CASE
WHEN T2."OnHand" < (T1."BaseQty" - T1."IssuedQty")
THEN 'SIN STOCK PARA COMPLETAR'
ELSE 'STOCK SUFICIENTE'
END AS 'Alerta Stock'
FROM OWOR T0
INNER JOIN WOR1 T1 ON T1."DocEntry" = T0."DocEntry"
INNER JOIN OITM T2 ON T2."ItemCode" = T1."ItemCode"
WHERE T0."Status" = 'R'
AND (T1."BaseQty" - T1."IssuedQty") > 0
ORDER BY T0."DocNum", T1."ItemCode"
SAP HANA
-- Componentes pendientes por orden de producción liberada
SELECT
T0."DocNum" AS "Orden Producción",
T0."ItemCode" AS "Producto Terminado",
T1."ItemCode" AS "Componente",
T2."ItemName" AS "Descripción Componente",
T1."BaseQty" AS "Cantidad Requerida",
T1."IssuedQty" AS "Cantidad Entregada",
T1."BaseQty" - T1."IssuedQty" AS "Pendiente",
T2."OnHand" AS "Stock Disponible",
CAST(
CASE WHEN T1."BaseQty" > 0
THEN (T1."IssuedQty" * 100.0 / T1."BaseQty")
ELSE 0
END AS DECIMAL(10,2)
) AS "% Avance",
CASE
WHEN T2."OnHand" < (T1."BaseQty" - T1."IssuedQty")
THEN 'SIN STOCK PARA COMPLETAR'
ELSE 'STOCK SUFICIENTE'
END AS "Alerta Stock"
FROM OWOR T0
INNER JOIN WOR1 T1 ON T1."DocEntry" = T0."DocEntry"
INNER JOIN OITM T2 ON T2."ItemCode" = T1."ItemCode"
WHERE T0."Status" = 'R'
AND (T1."BaseQty" - T1."IssuedQty") > 0
ORDER BY T0."DocNum", T1."ItemCode"
Variations and Advanced Use Cases
The MRP Wizard adapts to different business scenarios. You can create multiple scenarios for different horizons: a weekly one for urgent purchasing and a monthly one for strategic planning. Each scenario saves its own configuration and can be run independently.
For companies with multiple warehouses, MRP can generate transfer recommendations between locations. For example, if your central warehouse has a surplus of a component that is missing at the production plant, the system recommends a transfer instead of a new purchase. That way you optimise working capital without increasing total inventory.
Another valuable use case is planning with forecasts. If your company has strong seasonality, you can load sales forecasts and MRP will treat them as future demand, generating early purchasing recommendations. Bear in mind, though, that forecast quality determines recommendation quality.

Best Practices and Common Mistakes
Run MRP regularly. An MRP that runs once a month loses its value. The recommendation is to run it at least weekly, ideally twice a week in active manufacturing environments. That way your recommendations always reflect the current reality of the business.
Keep master data up to date. MRP is only as good as the data feeding it. Outdated lead times, incomplete bills of materials or badly configured minimum levels produce wrong recommendations. Set up a quarterly master data review process.
Don't ignore transfer recommendations. Many companies only convert the purchase recommendations and ignore the transfers. Yet transfers between warehouses are usually the fastest and cheapest way to resolve a shortfall.
Common mistake: trusting the quantities blindly. MRP calculates mathematically optimal quantities, but it does not account for constraints such as supplier minimum order quantities, storage capacity or economic production batches. Always review quantities before generating documents. Also adjust the order multiple and minimum quantity parameters in the item master to refine the recommendations.
Common mistake: too short a horizon. If your main supplier has a 45-day lead time and you plan only 30 days out, MRP will never generate recommendations in time. Make sure the horizon covers at least the longest lead time in your supply chain.
Official SAP Resources
To go deeper into MRP configuration, SAP offers detailed documentation on its help portal. The free course Managing Logistics in SAP Business One on the SAP Learning site includes a specific module on the MRP process. The implementation guide How to Configure and Use MRP in SAP Business One available on the SAP Help Portal covers all the wizard's advanced parameters.
Conclusion: From Chaos to Intelligent Planning
The SAP Business One MRP Wizard turns material management from a reactive process into a predictive one. You no longer need to wait until a component runs out to act; the system tells you in advance what you need, when you need it and how to get it.
The key is discipline: configure your master data properly, run MRP regularly and review the recommendations before executing them. As a result, you will cut production stoppages, optimise your inventory and meet delivery dates for your customers.
If you are a subscriber to the Strategic Circle, you have access to every article in this series, where we cover everything from advanced queries to configurations that turn SAP Business One into a real competitive advantage. Don't let your ERP be just a system of record: turn it into your strategic planning tool.